Given $n$ jobs, schedule them such that the weighted sum is minimum.

weighted minimum sum S for the schedule $\sigma = \{ J_1, J_2, ... J_n \}$ is given by :

$S = \sum_{1\leqq i \leqq n} w_i C_i$ where $C_i\ = \sum_{1\leqq j \leqq i} t_j$ and $w_i$ is the weight of job $J_i$, $t_i$ is the time $J_i$ takes to complete.

I think the solution is to schedule the jobs in shortest weighted processing time i.e. to arrange them in the increasing order of $ t_i/w_i $.

But how to prove this.

share|improve this question
add comment

1 Answer 1

Hint: Let $\sigma$ be the optimal schedule. Suppose that jobs $k$ and $k+1$ are switched. How is the cost affected? What does the optimality of $\sigma$ tell us about $w_k,w_{k+1},t_k,t_{k+1}$?

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.